Vitreous LabsEnergy transparency

Alcázar 2

A battery installation of 16.5 MW and 33 MWh in Alcázar de San Juan, Ciudad Real, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power16.5 MW
Storage33 MWh
Hours at full power2.0
PromoterGalp Energía España, SAU
Also namedPLANTA SOLAR ALCÁZAR 2, S.L.
ConfigurationAdded to a plant
Plant it is added toParque Fotovoltaico existente Alcázar 2, 45 MW, solar
MunicipalityAlcázar de San Juan
ProvinceCiudad Real
SubstationArenas de San Juan 220 kV
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
29 Aug 2024Public consultation; 16.5 MW, 33.2 MWhDelegación del Gobierno en Castilla-La ManchaBOE-B-2024-30384
27 Jan 2026Environmental decision; 16.5 MW, 33 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2026-2013

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.

All installations  ·  On the map  ·  Galp Energía España, SAU