BESS Zancones

A battery installation of 2.9 MW and 5.8 MWh in Villafranca de los Barros, Badajoz, first authorisation. Every fact below is taken from the latest act in the regional gazette of Extremadura that states it, and every act is linked.

In the gazette

Battery power2.9 MW
Storage5.8 MWh
Hours at full power2.0
PromoterEstrimal Energías Verdes, SL
ConfigurationAdded to a plant
Plant it is added toZancones, solar
MunicipalityVillafranca de los Barros
ProvinceBadajoz
Step reachedFirst authorisation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
29 Jul 2025Public consultation; 2.9 MWCONSEJERÍA DE AGRICULTURA, GANADERÍA Y DESARROLLO SOSTENIBLEDOE-25081225
5 Aug 2026First authorisation (autorización administrativa previa); 2.9 MW, 5.8 MWhCONSEJERÍA DE INDUSTRIA, ENERGÍA, CIENCIA Y TERRITORIODOE-26062010

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Extremadura, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.