Solaria-Santiz I
A battery installation of 20 MW and 100 MWh in Valdelosa, Salamanca, authorised to build. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 20 MW |
| Storage | 100 MWh |
| Hours at full power | 5.0 |
| Promoter | Planta FV100, SL |
| Configuration | Added to a plant |
| Plant it is added to | FV Solaria-Santiz I, 50 MW, solar |
| Access capacity | 42.1 MW |
| Municipality | Valdelosa |
| Province | Salamanca |
| Substation | Santiz 220 kV |
| Step reached | Authorised to build |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 14 Apr 2026 | Public consultation; 20 MW, 80 MWh | Subdelegación del Gobierno en Salamanca | BOE-B-2026-11545 |
| 20 Oct 2026 | First authorisation (autorización administrativa previa), authorisation to build (autorización administrativa de construcción); 20 MW, 100 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2026-21855 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.