HIB Alconchel 2020.2

A battery installation of 10 MW and 20 MWh in Barcarrota, Badajoz, first authorisation. Every fact below is taken from the latest act in the regional gazette of Extremadura that states it, and every act is linked.

In the gazette

Battery power10 MW
Storage20 MWh
Hours at full power2.0
PromoterAlter Enersun Badajoz, SL
ConfigurationAdded to a plant
Plant it is added toAlconchel 2020.2, solar
MunicipalityBarcarrota
ProvinceBadajoz
Step reachedFirst authorisation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
10 Jul 2025Public consultation; 10 MW, 20 MWhCONSEJERÍA DE AGRICULTURA, GANADERÍA Y DESARROLLO SOSTENIBLEDOE-25081054
17 Jun 2026First authorisation (autorización administrativa previa); 10 MW, 20 MWhCONSEJERÍA DE INDUSTRIA, ENERGÍA, CIENCIA Y TERRITORIODOE-26061525

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Extremadura, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.