A battery installation of 20 MW and 40 MWh in San Andrés del Rey, Guadalajara, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power20 MW
Storage40 MWh
Hours at full power2.0
PromoterPlanta FV 155 SL
ConfigurationAdded to a plant
Plant it is added toTelesto 2, solar
MunicipalitySan Andrés del Rey
ProvinceGuadalajara
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
25 Mar 2026Environmental decision; 20 MW, 40 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2026-6958

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.