El Cuco

A battery installation of 33.6 MW and 100 MWh in Montealegre del Castillo, Albacete, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power33.6 MW
Storage100 MWh
Hours at full power3.0
PromoterEL CUCO ENERGY, S.L.
ConfigurationAdded to a plant
Plant it is added toEl Cuco, 39.7 MW, solar
MunicipalityMontealegre del Castillo
ProvinceAlbacete
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
19 Jun 2026Public consultation; 33.6 MW, 100 MWhSubdelegación del Gobierno en Albacete, Dependencia de Industria y EnergíaBOE-B-2026-20852

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.