i-STENTORE (Sistema de almacenamiento mediante baterías e inversor)

A battery installation of 1.1 MW and 0.5 MWh in Albuñol, Granada, authorised to build. Every fact below is taken from the latest act in the regional gazette of Andalucía that states it, and every act is linked.

In the gazette

Battery power1.1 MW
Storage0.5 MWh
Hours at full power0.4
PromoterCuerva Energía, S.L.U.
ConfigurationStand-alone
MunicipalityAlbuñol
ProvinceGranada
Step reachedAuthorised to build

Every act, oldest first

PublishedWhat the act doesAuthorityAct
23 May 2025Environmental decisionConsejería de Sostenibilidad y Medio AmbienteBOJA-2025-97-36
15 Apr 2026Authorisation to build (autorización administrativa de construcción); 1.1 MW, 0.5 MWhConsejería de Economía, Hacienda, Fondos Europeos y Diálogo SocialBOJA-2026-71-29

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Andalucía, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.