PS10 BESS
A battery installation of 5 MW and 10 MWh in Sanlúcar la Mayor, Sevilla, in public consultation. Every fact below is taken from the latest act in the regional gazette of Andalucía that states it, and every act is linked.
In the gazette
| Battery power | 5 MW |
| Storage | 10 MWh |
| Hours at full power | 2.0 |
| Promoter | Sanlucar Solar S.A. |
| Configuration | Added to a plant |
| Plant it is added to | PS 10 (solar-thermal tower), solar thermal |
| Municipality | Sanlúcar la Mayor |
| Province | Sevilla |
| Substation | SET SANLUC_M |
| Step reached | In public consultation |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 26 Jan 2024 | Public consultation; 1 MW, 2.9 MWh | Consejería de Economía, Hacienda y Fondos Europeos - Consejería de Industria, Energía y Minas | BOP-SE-2024-019041 |
| 19 Nov 2024 | Public consultation; 5 MW, 10 MWh | Consejería de Economía, Hacienda y Fondos Europeos - Consejería de Industria, Energía y Minas | BOP-SE-2024-225045 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Andalucía, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.