Vitreous LabsEnergy transparency

Centro de transformación Penarrubia con almacenamiento de energía por baterías

A battery installation in Lugo, Lugo, authorised to build. Every fact below is taken from the latest act in the regional gazette of Galicia that states it, and every act is linked.

In the gazette

Battery powernot stated in any act
PromoterBEGASA
ConfigurationNot stated
MunicipalityLugo
ProvinceLugo
Step reachedAuthorised to build

Every act, oldest first

PublishedWhat the act doesAuthorityAct
3 May 2024Authorisation to build (autorización administrativa de construcción)Consellería de Economía, Industria e InnovaciónDOG-G0692-010324-0010

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Galicia, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.

All installations  ·  On the map