BESS Hibridación FV Andévalo
A battery installation of 26.4 MW and 59.9 MWh in Puebla de Guzmán, Huelva, authorised to build. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 26.4 MW |
| Storage | 59.9 MWh |
| Hours at full power | 2.3 |
| Promoter | Iberdrola Renovables Andalucía, SAU |
| Configuration | Added to a plant |
| Plant it is added to | FV Andévalo, 42.6 MW, solar |
| Access capacity | 26.4 MW |
| Municipality | Puebla de Guzmán |
| Province | Huelva |
| Substation | Puebla de Guzmán 220 kV |
| Step reached | Authorised to build |
This installation is registered to trade on OMIE as Andévalo, traded by Iberdrola Energía España.
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 13 Jul 2024 | Public consultation; 26.4 MW | Subdelegación del Gobierno en Huelva | BOE-B-2024-26379 |
| 15 Sep 2025 | First authorisation (autorización administrativa previa), authorisation to build (autorización administrativa de construcción); 26.4 MW, 59.9 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2025-18285 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.