Broza Solar

A battery installation of 10.9 MW and 21.8 MWh in Horche, Guadalajara, first authorisation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power10.9 MW
Storage21.8 MWh
Hours at full power2.0
PromoterBroza Solar, SLU
ConfigurationAdded to a plant
Plant it is added toBroza Solar, 31.5 MW, solar
Access capacity42.4 MW
MunicipalityHorche
ProvinceGuadalajara
SubstationArdoz 220 kV
Step reachedFirst authorisation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
8 Jan 2025Environmental decision; 10.9 MW, 21.8 MWhMinistry for the Ecological Transition, Directorate-General for Environmental Quality and AssessmentBOE-A-2025-393
5 Jun 2025Public consultation; 10.9 MW, 21.8 MWhSubdelegación del Gobierno en GuadalajaraBOE-B-2025-20846
9 Oct 2025First authorisation (autorización administrativa previa); 10.9 MWMinistry for the Ecological Transition, Directorate-General for Energy Policy and MinesBOE-A-2025-20191

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.