Vitreous LabsEnergy transparency

BESS Los Pedreros

A battery installation of 25.1 MW and 5,015 MWh in Fuente-Álamo, Albacete, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power25.1 MW
Storage5,015 MWh
Hours at full power200.0
ConfigurationAdded to a plant
Plant it is added toLos Pedreros, 50 MW
MunicipalityFuente-Álamo
ProvinceAlbacete
SubstationLa Pinilla 400 kV
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
27 Oct 2026Public consultation; 25.1 MW, 5,015 MWh·BOE-B-2026-35162*

The acts marked with an asterisk have so far been read only by our parser, which can mistake a plant’s power for the battery’s; the full reading, with every figure checked against the act’s words, follows within a week. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.

All installations  ·  On the map