A battery installation of 48.9 MW and 196 MWh in Valladolid, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power48.9 MW
Storage196 MWh
Hours at full power4.0
Promoterprocedimiento simplificado
ConfigurationAdded to a plant
Plant it is added tos respectivas instalaciones solares fotovoltaicas El Caballero
ProvinceValladolid
SubstationOlmedo 400 kV
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
21 Nov 2026Public consultation; 48.9 MW, 196 MWh·BOE-B-2026-38457*

The acts marked with an asterisk have so far been read only by our parser, which can mistake a plant’s power for the battery’s; the full reading, with every figure checked against the act’s words, follows within a week. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.

All installations  ·  On the map  ·  procedimiento simplificado