A battery installation of 0.6 MW and 0.9 MWh in Cillorigo de Liébana, Cantabria, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power0.6 MW
Storage0.9 MWh
Hours at full power1.5
PromoterViesgo Distribución Eléctrica, S.L.
ConfigurationStand-alone
MunicipalityCillorigo de Liébana
ProvinceCantabria
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
19 Sep 2022Public consultation; 0.6 MW, 0.9 MWhGobierno de Cantabria (DG Industria, Energía y Minas)BOE-B-2022-28296

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.