ALM Ictio Alcázar II
A battery installation of 20 MW and 80 MWh in Alcázar de San Juan, Ciudad Real, first authorisation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 20 MW |
| Storage | 80 MWh |
| Hours at full power | 4.0 |
| Promoter | Ictio Solar Auriga, SL |
| Configuration | Added to a plant |
| Plant it is added to | FV Ictio Alcázar II, 47.2 MW, solar |
| Access capacity | 44.4 MW |
| Municipality | Alcázar de San Juan |
| Province | Ciudad Real |
| Substation | Arenas de San Juan 220 kV |
| Step reached | First authorisation |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 7 Jun 2024 | Public consultation; 20 MW, 80 MWh | Delegación del Gobierno en Castilla-La Mancha | BOE-B-2024-20800 |
| 29 Nov 2025 | Environmental decision; 20 MW, 80 MWh | Ministry for the Ecological Transition, Directorate-General for Environmental Quality and Assessment | BOE-A-2025-24234 |
| 14 Oct 2026 | First authorisation (autorización administrativa previa); 20 MW, 80 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2026-21433 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.