Fregenal Alcalá I
A battery installation of 5 MW and 20 MWh in Sevilla, Sevilla, authorised to build. Every fact below is taken from the latest act in the regional gazette of Andalucía that states it, and every act is linked.
In the gazette
| Battery power | 5 MW |
| Storage | 20 MWh |
| Hours at full power | 4.0 |
| Promoter | Fregenal Solar S.L. |
| Configuration | Stand-alone |
| Municipality | Sevilla |
| Province | Sevilla |
| Substation | LSMT AIRT_S_ELV |
| Step reached | Authorised to build |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 9 Oct 2025 | Public consultation; 5 MW, 20 MWh | Consejería de Economía, Hacienda y Fondos Europeos - Consejería de Industria, Energía y Minas | BOP-SE-2025-195034 |
| 14 May 2026 | Authorisation to build (autorización administrativa de construcción); 5 MW, 20 MWh | Consejería de Economía, Hacienda y Fondos Europeos - Consejería de Industria, Energía y Minas | BOP-SE-2026-091035 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Andalucía, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.