Planta almacenamiento Bess Humanes 1

A battery installation of 5 MW and 10 MWh in Humanes de Madrid, Madrid, environmental decision. Every fact below is taken from the latest act in the regional gazette of Madrid that states it, and every act is linked.

In the gazette

Battery power5 MW
Storage10 MWh
Hours at full power2.0
PromoterEFM Solar 28, S. L.
ConfigurationStand-alone
MunicipalityHumanes de Madrid
ProvinceMadrid
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
3 Jul 2026Public consultation; 5 MW, 10 MWhCONSEJERÍA DE MEDIO AMBIENTE, AGRICULTURA E INTERIORBOCM-20260703-35
15 Oct 2026Environmental decisionCONSEJERÍA DE MEDIO AMBIENTE, AGRICULTURA E INTERIORBOCM-20261015-41

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Madrid, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.