Vitreous LabsEnergy transparency

Castillo Garcimuñoz

A battery installation of 19.5 MW and 39 MWh in Pinarejo, Cuenca, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power19.5 MW
Storage39 MWh
Hours at full power2.0
PromoterEDP RENOVABLES ESPAÑA S.L.U
ConfigurationAdded to a plant
Plant it is added toCastillo Garcimuñoz, 25.5 MW, solar and wind
MunicipalityPinarejo
ProvinceCuenca
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
29 Sep 2026Public consultation; 19.5 MW, 39 MWhSubdelegación del Gobierno en CuencaBOE-B-2026-31550

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.

All installations  ·  On the map  ·  EDP RENOVABLES ESPAÑA S.L.U