Parque Eólico Muel (repotenciación e hibridación, almacenamiento)
A battery installation of 3 MW and 6.7 MWh in Muel, Zaragoza, environmental decision. Every fact below is taken from the latest act in the regional gazette of Aragón that states it, and every act is linked.
In the gazette
| Battery power | 3 MW |
| Storage | 6.7 MWh |
| Hours at full power | 2.2 |
| Promoter | RWE Renewables Iberia, SAU |
| Configuration | Added to a plant |
| Plant it is added to | Parque Eólico Muel (repowered 16,2 MW) + PV 10 MW, wind + solar |
| Municipality | Muel, La Muela |
| Province | Zaragoza |
| Substation | Muel 132/30 kV |
| Step reached | Environmental decision |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 26 Jan 2024 | Public consultation; 3 MW, 6.7 MWh | VICEPRESIDENCIA SEGUNDA DEL GOBIERNO Y DEPARTAMENTO DE ECONOMÍA, EMPLEO E INDUSTRIA | BOA-007938699 |
| 31 Jan 2025 | Environmental decision; 3 MW | DEPARTAMENTO DE MEDIO AMBIENTE Y TURISMO | BOA-007946608 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Aragón, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.