Vitreous LabsEnergy transparency

Parque Eólico Muel (repotenciación e hibridación, almacenamiento)

A battery installation of 3 MW and 6.7 MWh in Muel, Zaragoza, environmental decision. Every fact below is taken from the latest act in the regional gazette of Aragón that states it, and every act is linked.

In the gazette

Battery power3 MW
Storage6.7 MWh
Hours at full power2.2
PromoterRWE Renewables Iberia, SAU
ConfigurationAdded to a plant
Plant it is added toParque Eólico Muel (repowered 16,2 MW) + PV 10 MW, wind + solar
MunicipalityMuel, La Muela
ProvinceZaragoza
SubstationMuel 132/30 kV
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
26 Jan 2024Public consultation; 3 MW, 6.7 MWhVICEPRESIDENCIA SEGUNDA DEL GOBIERNO Y DEPARTAMENTO DE ECONOMÍA, EMPLEO E INDUSTRIABOA-007938699
31 Jan 2025Environmental decision; 3 MWDEPARTAMENTO DE MEDIO AMBIENTE Y TURISMOBOA-007946608

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Aragón, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.

All installations  ·  On the map