A battery installation of 17.6 MW and 35.1 MWh in Pedrola, Zaragoza, authorised to build. Every fact below is taken from the latest act in the regional gazette of Aragón that states it, and every act is linked.

In the gazette

Battery power17.6 MW
Storage35.1 MWh
Hours at full power2.0
PromoterGrupo Desarrollos Energéticos Naturales, SL
ConfigurationAdded to a plant
Plant it is added toParque eólico Río Ebro II + PV 7,5 MW, wind + solar
MunicipalityPedrola
ProvinceZaragoza
SubstationEntrerrios 45 kV
Step reachedAuthorised to build

Every act, oldest first

PublishedWhat the act doesAuthorityAct
2 Sep 2024Public consultationDEPARTAMENTO DE MEDIO AMBIENTE Y TURISMOBOA-007943369
16 Jul 2025Environmental decision; 13.8 MW, 27.5 MWhDEPARTAMENTO DE MEDIO AMBIENTE Y TURISMOBOA-007950837
1 Jul 2026Authorisation to build (autorización administrativa de construcción); 17.6 MW, 35.1 MWhDEPARTAMENTO DE ECONOMÍA, COMPETITIVIDAD Y EMPLEOBOA-007959545

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Aragón, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.