Hibridación OPDE Belinchón 2
A battery installation of 26.7 MW and 126 MWh in Barajas de Melo, Cuenca, authorised to build. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 26.7 MW |
| Storage | 126 MWh |
| Hours at full power | 4.7 |
| Promoter | Planta Solar OPDE 52, SL |
| Configuration | Added to a plant |
| Plant it is added to | OPDE Belinchón 2, 48.1 MW, solar |
| Access capacity | 26.7 MW |
| Municipality | Barajas de Melo |
| Province | Cuenca |
| Substation | Belinchón 400 kV |
| Step reached | Authorised to build |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 5 Feb 2026 | Public consultation; 26.7 MW, 126 MWh | Subdelegación del Gobierno en Cuenca | BOE-B-2026-3174 |
| 20 Jun 2026 | First authorisation (autorización administrativa previa), authorisation to build (autorización administrativa de construcción); 26.7 MW, 126 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2026-13452 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.