A battery installation in Cerceda, A Coruña, environmental decision. Every fact below is taken from the latest act in the regional gazette of Galicia that states it, and every act is linked.

In the gazette

Battery powernot stated in any act
Storage16.2 MWh
PromoterGobela GE, S.L.U.
ConfigurationNot stated
MunicipalityCerceda
ProvinceA Coruña
Step reachedEnvironmental decision

Every act, oldest first

PublishedWhat the act doesAuthorityAct
21 Nov 2025Public consultation; 16.2 MWhConsellería de Economía e IndustriaDOG-G0763-131125-0004
16 Apr 2026Environmental decision; 16.2 MWhConsellería de Medio Ambiente e Cambio ClimáticoDOG-G0760-010426-0004

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Galicia, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.