A battery installation of 8 MW in Majadas de Tiétar, Cáceres, in public consultation. Every fact below is taken from the latest act in the regional gazette of Extremadura that states it, and every act is linked.

In the gazette

Battery power8 MW
PromoterPlanta FV 137, SL
ConfigurationAdded to a plant
Plant it is added toBaldío 2, solar
MunicipalityMajadas de Tiétar
ProvinceCáceres
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
12 Jun 2026Public consultation; 8 MWCONSEJERÍA DE INDUSTRIA, ENERGÍA, CIENCIA Y TERRITORIODOE-26080898

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Extremadura, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.

All installations  ·  On the map