A battery installation of 50 MW and 200 MWh in Logrosán, Cáceres, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 50 MW |
| Storage | 200 MWh |
| Hours at full power | 4.0 |
| Promoter | Solaben Electricidad Seis, S.A.U. |
| Also named | Solaben Electricidad Uno, S.A.U. |
| Configuration | Added to a plant |
| Plant it is added to | Solaben ST1, 50 MW, solar |
| Access capacity | 105 MW |
| Municipality | Logrosán |
| Province | Cáceres |
| Step reached | In public consultation |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 9 Jul 2026 | Public consultation; 50 MW, 200 MWh | Delegación del Gobierno en Extremadura | BOE-B-2026-23609 |
| 9 Jul 2026 | Public consultation; 50 MW, 200 MWh | Delegación del Gobierno en Extremadura | BOE-B-2026-23609 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.