Unnamed storage (BOE-B-2023-18032)
A battery installation of 90 MW and 67.5 MWh in Sant Antoni de Portmany, Illes Balears, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 90 MW |
| Storage | 67.5 MWh |
| Hours at full power | 0.8 |
| Promoter | Red Eléctrica de España, Sociedad Anónima Unipersonal |
| Configuration | Stand-alone |
| Municipality | Sant Antoni de Portmany |
| Province | Illes Balears |
| Substation | San Antonio 66 kV |
| Step reached | In public consultation |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 13 Jun 2023 | Public consultation; 90 MW, 67.5 MWh | Govern de les Illes Balears (Consejería de Transición Energética) | BOE-B-2023-18032 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.
All installations · On the map · Red Eléctrica de España, Sociedad Anónima Unipersonal