Hernán Cortés
A battery installation of 38.5 MW and 60 MWh in Logrosán, Cáceres, first authorisation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 38.5 MW |
| Storage | 60 MWh |
| Hours at full power | 1.6 |
| Promoter | Dehesa de los Guadalupes Solar, SLU |
| Configuration | Added to a plant |
| Plant it is added to | FV Hernán Cortés, 38.9 MW, solar |
| Access capacity | 34.4 MW |
| Municipality | Logrosán |
| Province | Cáceres |
| Substation | Valdecaballeros 400 kV |
| Step reached | First authorisation |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 1 Apr 2023 | Public consultation; 60 MWh | Delegación del Gobierno en Extremadura | BOE-B-2023-9709 |
| 19 Dec 2025 | First authorisation (autorización administrativa previa); 38.5 MW, 60 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2025-26106 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.
All installations · On the map · Dehesa de los Guadalupes Solar, SLU