Tesouro Storage
A battery installation of 17.5 MW and 37 MWh in As Pontes de García Rodríguez, A Coruña, authorised to build. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 17.5 MW |
| Storage | 37 MWh |
| Hours at full power | 2.1 |
| Promoter | Enel Green Power España, SL |
| Configuration | Added to a plant |
| Plant it is added to | Tesouro, 50.4 MW, wind |
| Access capacity | 60 MW |
| Municipality | As Pontes de García Rodríguez |
| Province | A Coruña |
| Substation | Puentes G.R. 400 kV |
| Step reached | Authorised to build |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 28 Apr 2026 | Public consultation; 17.5 MW, 37 MWh | Delegación del Gobierno en Galicia | BOE-B-2026-13398 |
| 19 Oct 2026 | First authorisation (autorización administrativa previa), authorisation to build (autorización administrativa de construcción); 17.5 MW, 37 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2026-21769 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.