PB Navegantes 31

A battery installation of 30 MW and 96.8 MWh in Ayala, Araba/Álava, first authorisation. Every fact below is taken from the latest act in the regional gazette of the Basque Country that states it, and every act is linked.

In the gazette

Battery power30 MW
Storage96.8 MWh
Hours at full power3.2
PromoterArena Green Assets 4, S.L.U.
ConfigurationStand-alone
MunicipalityAyala
ProvinceAraba/Álava
SubstationST Aiala 30 kV (i-DE)
Step reachedFirst authorisation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
3 Sep 2024Environmental decision; 23 MW, 69 MWhIndustria, Transición Energética y SostenibilidadBOPV-2024-09-4116
14 Jan 2026Environmental decision; 30 MW, 96.8 MWhIndustria, Transición Energética y SostenibilidadBOPV-2026-01-163
18 May 2026First authorisation (autorización administrativa previa); 30 MW, 96.8 MWhIndustria, Transición Energética y SostenibilidadBOPV-2026-05-2090

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of the Basque Country, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.