Vitreous LabsEnergy transparency

PHFV CENTELLES

A battery installation of 5.5 MW and 33 MWh in Centelles, Barcelona, in public consultation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.

In the gazette

Battery power5.5 MW
Storage33 MWh
Hours at full power6.0
PromoterRENEW GREEN GENERATOR IV, S.L.
ConfigurationNot stated
MunicipalityCentelles
ProvinceBarcelona
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
20 Oct 2026Public consultation; 5.5 MW, 33 MWhGeneralitat de CatalunyaBOE-B-2026-34189

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.

All installations  ·  On the map  ·  RENEW GREEN GENERATOR IV, S.L.