Vitreous LabsEnergy transparency

Axpo Storage Porriño 4

A battery installation of 5 MW in O Porriño, Pontevedra, in public consultation. Every fact below is taken from the latest act in the regional gazette of Galicia that states it, and every act is linked.

In the gazette

Battery power5 MW
PromoterAxpo Storage ES3, S.L.
ConfigurationStand-alone
MunicipalityO Porriño
ProvincePontevedra
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
13 Mar 2026Public consultation; 5 MWConsellería de Economía e IndustriaDOG-G0763-160226-0001

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Galicia, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.