Cincinato
A battery installation of 30 MW and 60 MWh in Bodonal de la Sierra, Badajoz, first authorisation. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 30 MW net, 38.5 MW installed; the net figure from BOE-B-2023-4650: “ón para la instalación "Infraestructura de almacenamiento de energía eléctrica CINCINATO" de 38,5 MWp y 30 MWn” |
| Storage | 60 MWh |
| Hours at full power | 1.6 |
| Promoter | Seguidores Solares Planta 2, SLU |
| Configuration | Added to a plant |
| Plant it is added to | FV Cincinato, 44 MW, solar |
| Access capacity | 41.8 MW |
| Municipality | Bodonal de la Sierra |
| Province | Badajoz |
| Substation | Brovales 400 kV |
| Step reached | First authorisation |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 14 Feb 2023 | Public consultation; 30 MW, 60 MWh | Delegación del Gobierno en Extremadura (Área de Industria y Energía) | BOE-B-2023-4650 |
| 21 Aug 2025 | First authorisation (autorización administrativa previa); 38.5 MW, 60 MWh | Ministry for the Ecological Transition, Directorate-General for Energy Policy and Mines | BOE-A-2025-17073 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.