OPDE Miramundo
A battery installation of 24 MW and 121 MWh in Puerto Real, Cádiz, environmental decision. Every fact below is the gazette’s own, from the latest act that states it, and every act is linked.
In the gazette
| Battery power | 24 MW |
| Storage | 121 MWh |
| Hours at full power | 5.0 |
| Promoter | Planta Solar OPDE Extremadura 2, S.L. |
| Configuration | Added to a plant |
| Plant it is added to | Miramundo, 50 MW, solar |
| Municipality | Puerto Real |
| Province | Cádiz |
| Step reached | Environmental decision |
Every act, oldest first
| Published | What the act does | Authority | Act |
|---|---|---|---|
| 29 Nov 2025 | Environmental decision; 24 MW, 126 MWh | Ministry for the Ecological Transition, Directorate-General for Environmental Quality and Assessment | BOE-A-2025-24233 |
| 30 Jul 2026 | Public consultation; 24 MW, 121 MWh | Delegación del Gobierno en Sevilla | BOE-B-2026-25688 |
Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: Boletín Oficial del Estado. Basado en datos de la Agencia Estatal Boletín Oficial del Estado.