A battery installation of 33.7 MW and 148 MWh in Belchite, Zaragoza, in public consultation. Every fact below is taken from the latest act in the regional gazette of Aragón that states it, and every act is linked.

In the gazette

Battery power33.7 MW
Storage148 MWh
Hours at full power4.4
PromoterRima Energy, SL
ConfigurationAdded to a plant
Plant it is added toCampo Belchite 2 HBESS de 33
MunicipalityBelchite
ProvinceZaragoza
SubstationSET Campo de Belchite 30/132 kV to SET Fuendetodos Colectora
Step reachedIn public consultation

Every act, oldest first

PublishedWhat the act doesAuthorityAct
4 Jun 2026Public consultation; 33.7 MW, 148 MWhDEPARTAMENTO DE ECONOMÍA, COMPETITIVIDAD Y EMPLEOBOA-007958882