A battery installation of 5 MW and 20 MWh in Sanxenxo, Pontevedra, authorised to build. Every fact below is taken from the latest act in the regional gazette of Galicia that states it, and every act is linked.

In the gazette

Battery power5 MW
Storage20 MWh
Hours at full power4.0
PromoterSoner Sorolla, S.L.
ConfigurationStand-alone
MunicipalitySanxenxo
ProvincePontevedra
Step reachedAuthorised to build

Every act, oldest first

PublishedWhat the act doesAuthorityAct
13 Nov 2023Public consultation; 5 MWConsellería de Economía, Industria e InnovaciónDOG-G0692-311023-0005
29 May 2024Environmental decisionConsellería de Medio Ambiente e Cambio ClimáticoDOG-G0760-150524-0001
7 Aug 2024Public consultation; 5 MW, 20 MWhConsellería de Economía e IndustriaDOG-G0763-230724-0002
2 Dec 2024Authorisation to build (autorización administrativa de construcción); 5 MW, 20 MWhConsellería de Economía e IndustriaDOG-G0763-221124-0007

Each act was read in full and every figure checked against the act’s own words. Where acts differ, the latest act that authorises the installation gives the figure above. Source: the regional gazette of Galicia, read 26 to 27 October 2026; only facts are taken from it, and each act is linked.