Sweden · the named batteries
Kungälv (Flower)
Operating, 15 MW, in Kungälv (SE3), owned by Flower. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 15 MW |
| Status | Operating, as of 21 August 2024 |
| Owner’s date | 21 August 2024, actual |
| Municipality | Kungälv |
| Bidding zone | SE3, Stockholm |
| Placed on the map | at Kungälv, the seat of its municipality (GeoNames) |
Who is behind it
| Owner | Flower |
| Developer | Flower |
| Traded by | Flower |
Not published anywhere we have found: ultimate owner, built by, cells.
What the sources say
Flower's first battery developed, built and run by itself, "outside Gothenburg" (Flower); started on 21 August 2024. MWh not published.
Evidence and sources
- name, municipality, owner, developer, optimiser, power, bidding zone, status: mynewsdesk.com/se/flower/pressreleases/flower-aktiverar-flera-…
From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B004.