No word since its date, 70 MW, in Karlshamn (SE4), owned by Ingrid Capacity. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power70 MW
StatusNo word since its date, as of 22 September 2022
Owner’s date2024, expected
MunicipalityKarlshamn
Bidding zoneSE4, Malmö
Placed on the mapat Karlshamn, the seat of its municipality (GeoNames)

Who is behind it

OwnerIngrid Capacity
DeveloperIngrid Capacity

Not published anywhere we have found: ultimate owner, traded by, built by, cells.

What the sources say

Announced in 2022 as Sweden's largest battery, for the first half of 2024, with Destination Duveryd. No later release; Ingrid's Horsaryd battery, also in Karlshamn, is a separate project and is not added to it.

Evidence and sources

From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B036.