Operating, 40 MW · 40 MWh, in Mora (SE3), owned by Ellevio Energy Solutions. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power40 MW
Capacity40 MWh
Duration1.0 hours
StatusOperating, as of 1 June 2026
Owner’s dateJune 2026, actual
MunicipalityMora
Bidding zoneSE3, Stockholm
Placed on the mapat Mora, the seat of its municipality (GeoNames)

Who is behind it

OwnerEllevio Energy Solutions
Ultimate ownerEllevio
DeveloperEllevio Energy Solutions
Built byAlfen (TheBattery Elements)

Not published anywhere we have found: traded by, cells.

What the sources say

SVT reported it finished on 1 June 2026, 40 MW and 40 MWh. Alfen expected Mora and Söderala (80 MW and 80 MWh together) in the first half of 2025, and the Green Power Sweden list of January 2026 already counted Mora: the dates disagree and SVT's report is used.

Evidence and sources

From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B010.