Mora
Operating, 40 MW · 40 MWh, in Mora (SE3), owned by Ellevio Energy Solutions. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 40 MW |
| Capacity | 40 MWh |
| Duration | 1.0 hours |
| Status | Operating, as of 1 June 2026 |
| Owner’s date | June 2026, actual |
| Municipality | Mora |
| Bidding zone | SE3, Stockholm |
| Placed on the map | at Mora, the seat of its municipality (GeoNames) |
Who is behind it
| Owner | Ellevio Energy Solutions |
| Ultimate owner | Ellevio |
| Developer | Ellevio Energy Solutions |
| Built by | Alfen (TheBattery Elements) |
Not published anywhere we have found: traded by, cells.
What the sources say
SVT reported it finished on 1 June 2026, 40 MW and 40 MWh. Alfen expected Mora and Söderala (80 MW and 80 MWh together) in the first half of 2025, and the Green Power Sweden list of January 2026 already counted Mora: the dates disagree and SVT's report is used.
Evidence and sources
- name, municipality, owner, parent, developer, power, capacity, bidding zone, status: svt.se/nyheter/lokalt/dalarna/batteriparken-i-mora-ar-…
- builder: alfen.com/en/news/alfen-battery-systems-stabilise-energy-…
From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B010.