Sweden · the named batteries
Torsvik, Jönköping
Operating, 10 MW · 10 MWh, in Jönköping (SE3), owned by Jönköping Energi. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 10 MW |
| Capacity | 10 MWh |
| Duration | 1.0 hours |
| Status | Operating, as of 16 June 2025 |
| Owner’s date | 23 May 2025, actual |
| Municipality | Jönköping |
| Bidding zone | SE3, Stockholm |
| Placed on the map | at Jönköping, the seat of its municipality (GeoNames) |
Who is behind it
| Owner | Jönköping Energi |
| Traded by | Ntricity |
| Built by | PSW Power & Automation |
Not published anywhere we have found: ultimate owner, developer, cells.
What the sources say
At the Torsvik combined heat and power plant; inaugurated 23 May 2025. "10 MW/MWh" as published; prequalified for several reserve markets.
Evidence and sources
- name, municipality, owner, optimiser, builder, power, capacity, bidding zone, status: bioenergyinternational.com/jonkoping-energi-inaugurates-large-scale-batter…
From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B063.