Operating, 10 MW · 10 MWh, in Jönköping (SE3), owned by Jönköping Energi. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power10 MW
Capacity10 MWh
Duration1.0 hours
StatusOperating, as of 16 June 2025
Owner’s date23 May 2025, actual
MunicipalityJönköping
Bidding zoneSE3, Stockholm
Placed on the mapat Jönköping, the seat of its municipality (GeoNames)

Who is behind it

OwnerJönköping Energi
Traded byNtricity
Built byPSW Power & Automation

Not published anywhere we have found: ultimate owner, developer, cells.

What the sources say

At the Torsvik combined heat and power plant; inaugurated 23 May 2025. "10 MW/MWh" as published; prequalified for several reserve markets.

Evidence and sources

From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B063.