Vitreous LabsEnergy transparency

Hylte Paper battery park

Operating, size not stated by any source, 42 MWh, in Hylte, owned by Hylte Paper. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Powernot stated by any source
Capacity42 MWh
StatusOperating, as of 30 December 2024
Owner’s dateDecember 2024, actual
MunicipalityHylte
Placed on the mapat Hylte, the seat of its municipality (GeoNames)

Who is behind it

OwnerHylte Paper
Built bySoltech Energy Solutions

Not published anywhere we have found: ultimate owner, developer, traded by, cells.

What the sources say

Behind the meter at the paper mill, also supporting the regional grid; completed and in trial operation in December 2024. Soltech gives 42 MWh; the Green Power Sweden list gives "42 MW", probably the same figure. MW not stated by the builder.

Evidence and sources

From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B048.

All batteries  ·  On the map