Horsaryd
Announced, 100 MW · 200 MWh, in Karlshamn (SE4), owned by Ingrid Capacity. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 100 MW |
| Capacity | 200 MWh |
| Duration | 2.0 hours |
| Status | Announced, as of 17 April 2026 |
| Owner’s date | 2028, expected |
| Municipality | Karlshamn |
| Bidding zone | SE4, Malmö |
| Placed on the map | at Horsaryd, the place its name carries (GeoNames) |
Who is behind it
| Owner | Ingrid Capacity |
| Developer | Ingrid Capacity |
Not published anywhere we have found: ultimate owner, traded by, built by, cells.
What the sources say
Building permit received in March 2026; construction could start in 2026, operation in 2028 (Ingrid, 17 April 2026; Energy-Storage.news).
Evidence and sources
- name, municipality, owner, developer, status: newsroom.notified.com/ingrid-capacity-1/posts/pressreleases/ingrid-do…
- power, capacity: ingridcapacity.com/news/ingrid-capacity-initiates-the-design-phase…
- bidding zone: energy-storage.news/ingrid-capacity-launching-600mwh-of-new-sweden-…
From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B033.