Vasa Vind wind farm battery, Strömsund
No word since its date, 20 MW · 20 MWh, in Strömsund (SE2), owned by Vasa Vind. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.
The battery
| Power | 20 MW |
| Capacity | 20 MWh |
| Duration | 1.0 hours |
| Status | No word since its date, as of 25 January 2024 |
| Owner’s date | 2024, expected |
| Municipality | Strömsund |
| Bidding zone | SE2, Sundsvall |
| Placed on the map | at Strömsund, the seat of its municipality (GeoNames) |
Who is behind it
| Owner | Vasa Vind |
| Built by | Alfen (TheBattery Elements) |
Not published anywhere we have found: ultimate owner, developer, traded by, cells.
What the sources say
Beside one of Vasa Vind's wind farms, sharing its connection; due by the end of 2024 with black start. No word since that it runs.
Evidence and sources
- name, municipality, owner, builder, power, capacity, bidding zone, status: alfen.com/en/news/alfen-marks-first-battery-energy-storag…
From the owners’, developers’ and builders’ own releases and the press, read by Vitreous. Svenska kraftnät publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in each reserve market is on the markets page, for the market as a whole. List id SE-B081.