12 MW, 23 MWh (1.9 hours) in Gumtow, Brandenburg, registered as operating since 5 August 2026. Everything on this page is read from Germany’s register of power units and the other published records named beside each fact.

What it is

The register holds this battery as one unit.

UnitRegister numberMWMWhCommissionedBatteryGrid operator check
Gumtow_SO5 SpeicherSEE99126462327512235 August 2026Lithiumunder check

Power is the net power the operator registered, the most the unit may feed into the grid. Energy is the usable capacity of the unit’s installation. A grid operator check marked “checked” means the grid company has confirmed the entry; “under check” means it has not yet. On the large sites we compared, the register’s commissioning date often came months before the owner’s announced start, which suggests it records first energisation.

Who runs it and who owns it

Operator in the registerCommercial register entry, as the operator gave itSeat
HT clean energy GmbHAmtsgericht Ansbach HRB 8489Merkendorf, Bayern

Owner. ENSoXX Invest GmbH, Gunzenhausen two thirds and J.T. Holding GmbH, Merkendorf one third; their own shareholders were not checked, through ENSoXX Invest GmbH, Gunzenhausen (Amtsgericht Ansbach HRB 8293) 66.66 %; J.T. Holding GmbH, Merkendorf (Amtsgericht Ansbach HRB 7900) 33.33 %. Confirmed in the commercial register. Evidence: Shareholder list of HT clean energy GmbH (listed under its earlier name HT Energie GmbH), dated 9 July 2024, filed 20 August 2024; the only list on file. Checked 11 October 2026. Every battery of this family.

The register names the operator, the company that runs the unit. The owner behind it comes from the commercial register (Handelsregister) or the owner’s own publication, as marked. The register number is the one the operator typed in; on 11 October 2026 we found it wrong or missing for 26 of the companies we looked up.

Who trades it and what it is built from

No published source we have found names who trades this battery, who built it or whose cells it uses. Fields we cannot source are left out.

Where it connects

Grid companyE.DIS Netz GmbH
Connected athigh voltage (110 kV)
MunicipalityGumtow, district of Prignitz
StateBrandenburg
Land parcelGörike, 1 und 43/2, 44/2, 45/2, 46/2, 47/2, 48/2, 49/2, 50/2, 51/2
Registered position52.9586, 12.2273
Register locationSEL986085224305

As registered. The grid company and voltage come from the register’s public unit table; the position is the one the operator registered. See it on the Atlas.

What has changed in the register

First registered on 19 August 2026; last changed in the register on 19 August 2026. No change has shown in our reads since the first, on 10 October 2026.

What this page cannot show

Germany publishes no battery’s metered output. On 11 October 2026 we checked the four public sources that might carry it: the ENTSO-E Transparency Platform, SMARD, the yearly EEG data and the transmission companies’ redispatch records. None gives the output of any German battery, one by one or as a fleet. So this page cannot say what the battery exported, imported or earned, as Britain’s battery pages do.

Sources: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland, Namensnennung 2.0: the full export of 15 October 2026 and the public unit table of 15 October 2026. Company details from the register’s market actor table. Owners from the commercial register and the owners’ publications, as marked. Tender awards from the Bundesnetzagentur’s award lists.