PASM Großspeicher Münster

4 MW, 24 MWh (6 hours) in Münster, Nordrhein-Westfalen, registered as operating since 24 April 2024. Everything on this page is read from Germany’s register of power units and the other published records named beside each fact.

What it is

The register holds this battery as four units.

UnitRegister numberMWMWhCommissionedBatteryGrid operator check
PASM Großspeicher Münster I (Pixii)SEE9209362165451624 April 2024Lithiumchecked
PASM Großspeicher Münster IV (Intillion)SEE9461819385821613 October 2025Lithiumunder check
PASM Großspeicher Münster III (Pixii)SEE9798160609381613 October 2025Lithiumunder check
PASM Großspeicher Münster II (Intillion)SEE9959589080201624 April 2024Lithiumchecked

Power is the net power the operator registered, the most the unit may feed into the grid. Energy is the usable capacity of the unit’s installation. A grid operator check marked “checked” means the grid company has confirmed the entry; “under check” means it has not yet. On the large sites we compared, the register’s commissioning date often came months before the owner’s announced start, which suggests it records first energisation.

Who runs it and who owns it

Operator in the registerCommercial register entry, as the operator gave itSeat
PASM GmbHAmtsgericht München HRB 202919München, Bayern

Owner. Deutsche Telekom AG, through Deutsche Telekom AG (100%). From the owner’s own publication. Evidence: PASM (Power & Air Solutions) website, About us: "We are a wholly-owned subsidiary of Deutsche Telekom AG.". Checked 16 October 2026. Every battery of this family.

The register names the operator, the company that runs the unit. The owner behind it comes from the commercial register (Handelsregister) or the owner’s own publication, as marked. The register number is the one the operator typed in; on 11 October 2026 we found it wrong or missing for 26 of the companies we looked up.

Who trades it and what it is built from

No published source we have found names who trades this battery, who built it or whose cells it uses. Fields we cannot source are left out.

Where it connects

Grid companyStadtnetze Münster GmbH
Connected atmedium voltage
MunicipalityMünster
StateNordrhein-Westfalen
Registered position51.9501, 7.6660
Register locationSEL914568777550, SEL922658301776, SEL967827154814

As registered. The grid company and voltage come from the register’s public unit table; the position is the one the operator registered. See it on the Atlas.

What has changed in the register

First registered on 25 April 2024; last changed in the register on 23 October 2025. No change has shown in our reads since the first, on 10 October 2026.

What this page cannot show

Germany publishes no battery’s metered output. On 11 October 2026 we checked the four public sources that might carry it: the ENTSO-E Transparency Platform, SMARD, the yearly EEG data and the transmission companies’ redispatch records. None gives the output of any German battery, one by one or as a fleet. So this page cannot say what the battery exported, imported or earned, as Britain’s battery pages do.

Sources: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland, Namensnennung 2.0: the full export of 15 October 2026 and the public unit table of 15 October 2026. Company details from the register’s market actor table. Owners from the commercial register and the owners’ publications, as marked. Tender awards from the Bundesnetzagentur’s award lists.