Vitreous LabsEnergy transparency

Schaper Grid Energy Storage Herford

18 MW, 42 MWh (2.3 hours) in Herford, Nordrhein-Westfalen, registered as operating since 14 December 2022. Everything on this page is read from Germany’s register of power units and the other published records named beside each fact.

What it is

The register holds this battery as one unit.

UnitRegister numberMWMWhCommissionedBatteryGrid operator check
Schaper Grid Energy Storage HerfordSEE983264343635184214 December 2022Lithiumchecked

Power is the net power the operator registered, the most the unit may feed into the grid. Energy is the usable capacity of the unit’s installation. A grid operator check marked “checked” means the grid company has confirmed the entry; “under check” means it has not yet. On the large sites we compared, the register’s commissioning date often came months before the owner’s announced start, which suggests it records first energisation.

Who runs it and who owns it

Operator in the registerCommercial register entry, as the operator gave itSeat
Schaper Grid Energy Storage Füllenkamp GmbHAmtsgericht Bad Oeynhausen HRA 18821Herford, Nordrhein-Westfalen

Owner. Schaper Group. Reported in the trade press and not yet confirmed by the owner or the commercial register. Evidence: WAGO customer case study, undated: "the Schaper Group independently built and now operates". Checked 16 October 2026. Every battery of this family.

The register names the operator, the company that runs the unit. The owner behind it comes from the commercial register (Handelsregister) or the owner’s own publication, as marked. The register number is the one the operator typed in; on 11 October 2026 we found it wrong or missing for 26 of the companies we looked up.

Who trades it and what it is built from

Owner, as publishedSchaper Group built and operates the system WAGO customer case study
Trades its outputUnnamed marketing partner for primary and secondary control reserve and energy trading WAGO customer case study
Built bySchaper Group (self-built); WAGO supplied control, regulation and data technology WAGO customer case study
Energy, as the owner gives itAbout 20.8 built, expansion to 41.6 planned (register holds 41.6 MWh) WAGO customer case study
In operation, as the owner gives itGrid connected 2024-01-01; active in energy markets since 2024-09-10 (register 2022-12-14) WAGO customer case study

From published documents: the owners’, builders’ and optimisers’ own announcements and the trade press, each linked. Where the owner’s power or energy differs from the register’s, both are shown and every figure on this site uses the register’s.

Where it connects

Grid companyWestfalen Weser Netz GmbH
Connected atlow voltage
MunicipalityHerford
StateNordrhein-Westfalen
Registered position52.1301, 8.6561
Register locationSEL911842227916

As registered. The grid company and voltage come from the register’s public unit table; the position is the one the operator registered. See it on the Atlas.

What has changed in the register

First registered on 19 December 2023; last changed in the register on 18 March 2026. No change has shown in our reads since the first, on 10 October 2026.

What this page cannot show

Germany publishes no battery’s metered output. On 11 October 2026 we checked the four public sources that might carry it: the ENTSO-E Transparency Platform, SMARD, the yearly EEG data and the transmission companies’ redispatch records. None gives the output of any German battery, one by one or as a fleet. So this page cannot say what the battery exported, imported or earned, as Britain’s battery pages do.

Sources: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland, Namensnennung 2.0: the full export of 15 October 2026 and the public unit table of 15 October 2026. Company details from the register’s market actor table. Owners from the commercial register and the owners’ publications, as marked. Tender awards from the Bundesnetzagentur’s award lists.