Vitreous LabsEnergy transparency

SEE_2025_4642_Föhren_BESS

20 MW, 55 MWh (2.8 hours) in Föhren, Rheinland-Pfalz, registered as operating since 18 December 2025. Everything on this page is read from Germany’s register of power units and the other published records named beside each fact.

What it is

The register holds this battery as one unit.

UnitRegister numberMWMWhCommissionedBatteryGrid operator check
SEE_2025_4642_Föhren_BESSSEE926245506438205518 December 2025Lithiumchecked

Power is the net power the operator registered, the most the unit may feed into the grid. Energy is the usable capacity of the unit’s installation. A grid operator check marked “checked” means the grid company has confirmed the entry; “under check” means it has not yet. On the large sites we compared, the register’s commissioning date often came months before the owner’s announced start, which suggests it records first energisation.

Who runs it and who owns it

Operator in the registerCommercial register entry, as the operator gave itSeat
Schoenergie Batteriespeicher Föhren GmbHAmtsgericht Wittlich HRB 46439Föhren, Rheinland-Pfalz

Owner. Schoenergie, a family-owned German renewable energy company. Reported in the trade press and not yet confirmed by the owner or the commercial register. Evidence: enspired case study, 2 September 2026: "Schoenergie is a family-owned renewable energy company based in Germany.". Checked 16 October 2026. Every battery of this family.

The register names the operator, the company that runs the unit. The owner behind it comes from the commercial register (Handelsregister) or the owner’s own publication, as marked. The register number is the one the operator typed in; on 11 October 2026 we found it wrong or missing for 26 of the companies we looked up.

Who trades it and what it is built from

Owner, as publishedSchoenergie, family-owned German renewable energy company (asset owner not stated in so many words; register operator Schoenergie Batteriespeicher Föhren GmbH) enspired case study, 2 September 2026
Trades its outputenspired, cross-market optimisation since October 2025 enspired case study, 2 September 2026
Battery systemHiTHIUM battery containers; SMA grid-forming inverters enspired case study, 2 September 2026
Power, as the owner gives it21 (register holds 20.0 MW) enspired case study, 2 September 2026
Energy, as the owner gives it55 MWh enspired case study, 2 September 2026
In operation, as the owner gives itIn optimised operation since October 2025 (2025-10); register first commissioning 2025-12-18 enspired case study, 2 September 2026
Also publishedCo-located with a solar park in neighbouring Schweich enspired case study, 2 September 2026

From published documents: the owners’, builders’ and optimisers’ own announcements and the trade press, each linked. Where the owner’s power or energy differs from the register’s, both are shown and every figure on this site uses the register’s.

Where it connects

Grid companyWestnetz GmbH
Connected atthe high to medium voltage transformer level
MunicipalityFöhren, district of Trier-Saarburg
StateRheinland-Pfalz
Land parcelFöhren, Flur/Flurstück: 6-19/65
Registered position49.8536, 6.7876
Register locationSEL963692414107

As registered. The grid company and voltage come from the register’s public unit table; the position is the one the operator registered. See it on the Atlas.

What has changed in the register

First registered on 12 January 2026; last changed in the register on 12 January 2026. No change has shown in our reads since the first, on 10 October 2026.

What this page cannot show

Germany publishes no battery’s metered output. On 11 October 2026 we checked the four public sources that might carry it: the ENTSO-E Transparency Platform, SMARD, the yearly EEG data and the transmission companies’ redispatch records. None gives the output of any German battery, one by one or as a fleet. So this page cannot say what the battery exported, imported or earned, as Britain’s battery pages do.

Sources: Marktstammdatenregister, Bundesnetzagentur, Datenlizenz Deutschland, Namensnennung 2.0: the full export of 15 October 2026 and the public unit table of 15 October 2026. Company details from the register’s market actor table. Owners from the commercial register and the owners’ publications, as marked. Tender awards from the Bundesnetzagentur’s award lists.