AKKU One

Being built, 125 MW · 300 MWh, in Lapinlahti, owned by Covenergo (majority) with Delta Capacity. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power125 MW
Capacity300 MWh
Duration2.4 hours
StatusBeing built, as of 5 October 2026
Owner’s date2027 Q4, expected
MunicipalityLapinlahti
Placed on the mapat the centre of Lapinlahti, its municipality (GeoNames)

Who is behind it

OwnerCovenergo (majority) with Delta Capacity
DeveloperHelios Nordic Energy
Built byDelta Capacity (EPCM); NYAB (balance of plant); Sungrow (battery system); Rejlers (technical support); Ampner (grid studies); GreenPowerMonitor (EMS and SCADA)

Covenergo (Czech) majority with Delta Capacity (Swiss). No Finnish company for AKKU One found by name in YTJ.

Not published anywhere we have found: ultimate owner, cells. The page says so rather than guessing.

What the sources say

Delta Capacity (17 Sep 2026): construction under way, commissioning targeted for Q4 2027; bought ready to build from Helios Nordic Energy. Energy-Storage.news (9 Oct 2026) said Q4 of this year; the owners' release says Q4 2027. Centrica Energy partial toll (5 Oct 2026).

Evidence and sources

From the owners’, developers’ and builders’ own releases, council decisions and permit bulletins, read by Vitreous and checked against the owners’ own words on 12 October 2026; a bracket such as “(Energy-Storage.news only)” in a field means the trade press is still the only source for it. Fingrid publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Fingrid’s markets is on the markets page, for the whole market and never for a named battery. List id FI-B023.