Vitreous LabsEnergy transparency

Alapitkä battery park

Announced, 95 MW · 220 MWh, in Lapinlahti, owned by re:cap global investors (FP Lux European Battery Storage fund). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power95 MW
Capacity220 MWh
Duration2.3 hours
StatusAnnounced, as of 23 April 2026
Owner’s date2027, expected
MunicipalityLapinlahti
Placed on the mapat Alapitkä, the place its name carries (GeoNames)

Who is behind it

Ownerre:cap global investors (FP Lux European Battery Storage fund)
DeveloperSMA Altenso with Infinergies Finland Oy
Built bySMA Altenso (full EPC: balance of plant, medium to high voltage, grid integration); SMA (Sunny Central Storage UP-S grid-forming inverters)

A fund, no business ID. YTJ lists Altenso & Infinergies BESS 01 Oy (3579378-4) and 02 Oy (3579376-8); no source says which holds Alapitkä.

Not published anywhere we have found: ultimate owner, cells. The page says so rather than guessing.

What the sources say

SMA (23 Apr 2026): Battery Park Alapitkä, municipality of Lapinlahti, 95 MW / 220 MWh, ready to build, construction expected from spring 2026, operation in 2027 (corrected 12 Oct 2026: municipality was blank and the date was 2027 H2 from Energy-Storage.news).

Evidence and sources

From the owners’, developers’ and builders’ own releases, council decisions and permit bulletins, read by Vitreous and checked against the owners’ own words on 12 October 2026; a bracket such as “(Energy-Storage.news only)” in a field means the trade press is still the only source for it. Fingrid publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Fingrid’s markets is on the markets page, for the whole market and never for a named battery. List id FI-B045.

All batteries  ·  On the map