Kannisto wind farm BESS (OX2)

Being built, 125 MW · 250 MWh, in Halsua, owned by OX2. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power125 MW
Capacity250 MWh
Duration2.0 hours
StatusBeing built, as of 12 October 2026
Owner’s date2028, expected
MunicipalityHalsua
Placed on the mapat Kannisto, the place its name carries (GeoNames)

Who is behind it

OwnerOX2
DeveloperOX2

OX2. YTJ lists OX2 Finland Oy (3428523-5) and others but no company named for Kannisto storage.

Not published anywhere we have found: ultimate owner, built by, cells. The page says so rather than guessing.

What the sources say

CORRECTED 12 Oct 2026: size was 110 MW / 220 MWh from ESS News. OX2's own project page: "a 125-megawatt energy storage will be built as part of the project", 125 MW (250 MWh). Co-located with the Kannisto wind farm. Statkraft optimises (OX2, 25 Feb 2026).

Evidence and sources

From the owners’, developers’ and builders’ own releases, council decisions and permit bulletins, read by Vitreous and checked against the owners’ own words on 12 October 2026; a bracket such as “(Energy-Storage.news only)” in a field means the trade press is still the only source for it. Fingrid publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Fingrid’s markets is on the markets page, for the whole market and never for a named battery. List id FI-B026.