Lakiakangas wind farm storage (Helen, jointly owned)

Operating, 5 MW · 10 MWh, owned by Helen (jointly owned; partner not named). Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power5 MW
Capacity10 MWh
Duration2.0 hours
StatusOperating, as of 2 December 2025
Owner’s dateby 2024-02, actual
Placed on the mapnot placed: no municipality in any source

Who is behind it

OwnerHelen (jointly owned; partner not named)
Business ID2630573-4

YTJ, by exact name: Helen Oy (the owner Helen names itself as; its partner is not named). https://avoindata.prh.fi/opendata-ytj-api/v3/companies?businessId=2630573-4

Not published anywhere we have found: ultimate owner, developer, built by, cells. The page says so rather than guessing.

What the sources say

No source read names the municipality.

Evidence and sources

From the owners’, developers’ and builders’ own releases, council decisions and permit bulletins, read by Vitreous and checked against the owners’ own words on 12 October 2026; a bracket such as “(Energy-Storage.news only)” in a field means the trade press is still the only source for it. Fingrid publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Fingrid’s markets is on the markets page, for the whole market and never for a named battery. List id FI-B003.

All batteries  ·  On the map