Rautavaara (Winda Energy)

Being built, 30 MW · 60 MWh, in Rautavaara, owned by Winda Energy. Every fact below is as a published source states it, with the address beside it; a field not shown is one no source gave, and nothing is guessed.

The battery

Power30 MW
Capacity60 MWh
Duration2.0 hours
StatusBeing built, as of 13 January 2026
Owner’s date2026, expected
MunicipalityRautavaara
Placed on the mapat the centre of Rautavaara, its municipality (GeoNames)

Who is behind it

OwnerWinda Energy
Ultimate ownerBHM Renewables (majority shareholder of Winda)
DeveloperWinda Energy
Built byGAZ Energy (integrated battery); Ingeteam (inverter)
Business ID3168679-7

YTJ, by exact name: Winda Energy Oy. https://avoindata.prh.fi/opendata-ytj-api/v3/companies?businessId=3168679-7

Not published anywhere we have found: cells. The page says so rather than guessing.

What the sources say

Winda: construction from autumn 2025, commercial operation expected in 2026; with Second Foundation (route to market).

Evidence and sources

From the owners’, developers’ and builders’ own releases, council decisions and permit bulletins, read by Vitreous and checked against the owners’ own words on 12 October 2026; a bracket such as “(Energy-Storage.news only)” in a field means the trade press is still the only source for it. Fingrid publishes no meter, no price and no instruction per battery, so this page carries no money: what one megawatt is paid in Fingrid’s markets is on the markets page, for the whole market and never for a named battery. List id FI-B034.